The works formed part of the wider Alexandra Basin Regeneration Project and involved the construction of a new combi-wall and contiguous piled tie-back wall.
Due to the challenging Dublin Boulder Clay and the requirements of the permanent works design, a bespoke sequence of enabling and piling works was developed by Quinn Piling’s engineering team.
Piling Scope and Details
Quinn Piling’s works included:
- Installation and mucking-out of 110 no. 1,800mm diameter temporary pile casings
- Temporary casings installed to depths of approximately 27m
- Enabling works for the installation of 1,400mm diameter permanent steel tubular piles
- Installation of sheet piles between the permanent tubular piles
- Installation of 183 no. 750mm diameter CFA piles
- Construction of a contiguous piled tie-back wall
- Design and manufacture of bespoke pile-gate equipment
- Value engineering and manufacture of reinforcement cages
The large-diameter piling works extended through the Dublin Boulder Clay, with the permanent tubular piles subsequently driven approximately 9m deeper.
Challenges
The principal challenge was installing the combi-wall through the difficult Dublin Boulder Clay.
The permanent tubular piles could not be installed solely by driving, requiring Quinn Piling to develop an alternative methodology. Accurate positioning, verticality and rotation of the tubular piles were also critical to ensure the sheet piles could subsequently be installed between them without the risk of de-clutching.